Summit Carbon Solutions’ CO2 pipeline approved in Iowa
October 15, 2024

The Iowa Utilities Board (IUB) has approved Summit Carbon Solutions base pipeline project that will span around 688 miles and capture and store 12 million tonnes of carbon dioxide (CO2) annually.


Summit Carbon Solutions’ project has seen extensive scrutiny in the US state previously. The IUB carried out an extensive review process over the last 34 months, which was made up of 33 public informational meetings, a public hearing, and a review of around 50,000 pages, among other processes.


Post-review, the IUB unanimously found that Summit Carbon Solutions met the requirements of Iowa Code Chapter 479B and that the pipeline will provide a service that is in the public convenience and necessity.


In reaching its decision, the IUB applied a statutory balancing test, which found the public benefits of the project outweigh the private a public costs with the terms and conditions imposed by the IUB.


Before Summit Carbon Solutions starts construction, it must file proof of general liability insurance policy of no less than $100m to cover any damages related to the construction, operation, and maintenance of its Iowa pipeline.


Summit Carbon Solutions is also not allowed to begin construction in Iowa until it has obtained approval from North Dakota for the route and sequestration site and approval from South Dakota for the route.


The company has submitted a revised pipeline permit application to the North Dakota Public Service Commission, addressing previously raised concerns related to it its planned carbon capture pipeline.


Earlier this year, it was reported that Summit Carbon Solutions had secured 80% of the necessary right-of-way for the project. This highlighted its effort to adjust the pipeline route and take the state’s requests into consideration.


In September 2023, the South Dakota Public Utilities Commission (PC) denied Summit Carbon Solutions’ permit application. Since the rejection, Summit Carbon Solutions has announced plans to re-apply for the permit.


Lee Blank, CEO of Summit Carbon Solutions, said, “The momentum will continue as we prepare to file our South Dakota permit application in early July. We look forward to engaging with the state throughout this process and are confident in a successful outcome.”


Summit Carbon Solutions is partnering with 57 ethanol plants across five states and has signed voluntary easement agreements with 75% of Iowa landowners along this route. The company has said it will continue to work with landowners.


gasworld © 2024. All Rights Reserved

March 18, 2025
TORONTO, March 18, 2025 - VVC Exploration Corporation, dba VVC Resources, (“VVC”), (TSX-V:VVC and OTCQC:VVCVF) announces the following: Appointment of Officers The Directors appointed Mr. Bill Kerrigan as President and Chief Operating Officer of VVC. Mr. Kerrigan will continue to be President of Plateau Helium Corporation. Mr. James A. Culver will remain as CEO of VVC. VVC Chairman, Terrence Martell, commented, "As a representative of Management and the Board, I extend heartfelt gratitude to Mr. Culver for his years of service as President. I also welcome Mr. Kerrigan to his new role as President and I am confident that he will provide positive momentum for VVC." Option Grant The Directors also granted incentive stock options under its stock option plan, to officers, directors and consultants of the Company, to purchase up to an aggregate of 15,700,000 common shares, representing 2.74% of the outstanding shares of the Company. The stock options are exercisable at a price of CA$0.05 per share expiring March 17, 2035. 25% of the options granted will vest immediately with the remaining vesting at 25% every six months. The exercise price was fixed at the minimum allowable price by the TSX Venture Exchange policies. The options, granted in accordance with the provisions of the Company's stock option plan, are subject to the TSX Venture Exchange policies and the applicable securities laws. Of the Options granted, 41.1% were to Directors, 30.3% to Officers and 28.7% to Employees/Consultants of the Company. About VVC Resources VVC engages in the exploration, development, and management of natural resources - specializing in scarce and increasingly valuable materials needed to meet the growing, high-tech demands of industries such as manufacturing, technology, medicine, space travel, and the expanding green economy. Our portfolio includes a diverse set of multi-asset, high-growth projects, comprising: Helium & industrial gas production in western U.S.; Copper & associated metals operations in northern Mexico; and Strategic investments in carbon sequestration and other green energy technologies. VVC is a Canada-based, publicly-traded company on the TSXV (TSX-V:VVC). To learn more, visit our website at: www.vvcresources.com. Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.
December 5, 2024
The Company’s Annual General Meeting of Shareholders (“AGM”) took place virtually yesterday with 34 attendees (shareholders and guests). Total attendance in person and by proxy was 137 shareholders representing about 51.4% of the outstanding shares. At the AGM, shareholders approved the election of all Directors proposed by Management with over 90% of the tendered votes being in favor, and the re-appointment of MNP LLP as auditors of the Company with all of the tendered votes being in favor.
Show More >